Building Statistics
project constraints |
|
applicable codes |
International Building Code |
2000 |
|
International Mechanical Code |
2000 |
|
International Plumbing Code |
2000 |
|
National Electric Code |
1996 |
|
International Energy Conservation Code |
2000 |
|
ADAAG |
Latest Edition |
|
(Americans with Disabilities Act Accessibility Guidelines) |
|
Underwriters Laboratories, Inc. |
1998 |
|
District of Columbia Construction Codes |
2003 |
|
DCMR 13 Electrical and Mechanical |
|
|
DCMR 13A Elevators |
|
|
DC Law 8-36 Environmental Policy Act 1989 |
|
|
DCMR 12A Building Code Regulations |
2003 |
|
DCMR 12J Existing Building Code |
2000 |
|
|
|
zoning |
DCMR Title 11 dated February 2003 |
http://dcoz.dc.gov/info/reg.shtm |
|
District of Columbia Zoning Map |
Map 10 |
|
C-3-C Commercial District |
|
|
F.A.R. by Right |
6.5 |
|
Allowable Floor Area |
95,504.5 gross square feet |
|
Max Percentage of Lot Occupancy |
100% |
|
Max Building Height by Right |
90 feet |
|
with T.D.R.'s |
130 |
|
(Transfer Development Rights) |
|
|
Number of Floors above Grade |
No Limit |
|
Required Parking |
|
|
General Office |
1 every 1,800 g.s.f. above 2,000 g.s.f. |
|
Retail Use |
1 every 750 g.s.f. above 3,000 g.s.f. |
|
Penthouse |
Max Height 18'-6" with 1:1 set back |
|
|
|
historical requirements |
none |
|
|
|
|
architecture |
|
|
|
design and function |
The scope of this project includes the addition of three stories onto an existing occupied eight story building, extending the existing bank of three elevators while modernizing them up to a new elevator machine room on the penthouse level, and constructing a new penthouse and installing the necessary equipment. Taking a step back this project sits on Washington Circle which is located in a commercial district in the North West part of Washington DC at the intersection of 22nd and K Street. This project, as mentioned above, includes adding a |
Image Courtesy of DAVIS Construction |
|
three story steel structure with a penthouse onto an eight story concrete building constructed in the 1970’s. The façade of the new construction was designed to complement the existing portion of the building. There are several new additions to the exterior of the building. One of which is Tnemec Enviro-crete paint. The building from ground level to the eighth floor is getting a new coat of white paint to help it blend in with the new curtain wall system used on the ninth thru eleventh floors. As previously mentioned, the façade of the three new floors is comprised of a curtain wall system, ribbon windows, punch windows, metal panes, and a screen system. To make the buildings look more continuous throughout the entire height, an intricate louver system will be integrated into both new and existing construction. One additional feature of interest to the building is the installation of a green roof on a portion of the ninth floor. |
|
|
building enclosure |
|
|
|
building facade |
The existing building is brick which will be receiving a coating of Tnemec Enviro-crete paint. On the South and West elevations, a unitized curtain wall systems will be used. This system will be exterior glazed. Each unit is one floor in height and four feet wide. The North elevation is comprised of masonry with Henry Airbloc over sheating with punched windows. The masonry is covered with the same Tnemec paint as mentioned above but this is not intended to be the primary measure against water infiltration. |
Image Courtesy of DAVIS Construction |
|
The façade will drain at each floor slab where there will be an EPDM flashing system. These punched windows are also exterior glazed. Along with the punch windows, the North elevation will feature composite metal panels over the same Henry Airbloc sheathing. As for the East elevation, ribbon windows with masonry over Henry Airbloc over sheathing at spandrel areas will be used. The masonry assembly is of the same nature as on the North in terms of water resistance. Finally, the penthouse will be covered in ribbed composite panels with a Tyvek vapor barrier over sheathing. |
|
|
roofing |
The penthouse roof is comprised of several materials, first of which is the metal decking it all rests on. The roof deck used on this project is 3" deep rib, 20 gage galvanized metal deck. Above the metal deck sits a layer of rigid insulation which is to taper toward the roof drains to promote proper drainage. Next, there is a layer of single ply EPDM roof membrane with a gravel ballast. At all perimeter conditions, the EPDM must be continuous up and over the parapet and extend down as to overlap the facade material by two inches. Where there is to be a walkway there is to be |
Image Courtesy of DAVIS Construction |
|
two layers of a protective mat above the roof membrane and place roof pavers above. |
|
|
|
The other type of roofing is located on a portion of the ninth floor. In this location, a green roof was utilized. This roofing systems begins with the building existing roof as the substrate. Above this is the roofing membrane which is comprised of two layers of hot fluid applied roofing material. Next, there is a layer of felt followed by a protective layer, rigid insulation, moisture retention mats where needed, and filter fabric. On top of it all is a layer soil and vegetation which is to be at least three inches thick but not more than six inches thick and shall weight no more than eighteen pounds per square foot for a three inch green roof. |
Awaiting Image of Green Roof |
|
|
|
interior rendering |
|
|
|
|
|