Home
Student Bio
Building Statistics
Thesis Abstract
Technical Assignments
Thesis Research
Thesis Proposal
Presentation
Final Report
Reflection
Senior Thesis e-Studio

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Building Statistics

       
general building information
       
building name 2175 K Street NW    
location 2175 K Street NW Washington DC 20037
building occupants Starbucks  
George Washington University
US Chemical
European Union
function office building    
construction type occupied renovation
size 173,551 sq. ft. (139,860 sq. ft. existing; 33,691 sq. ft. new construction)
number of stories above 11 stories (8 existing; 3 new construction)
number of stories below 3 stories    
total number of stories 14 stories    
construction dates start February 2007 to be completed March 2011
building cost $15,477,718 from PCCO #005  
project delivery method CM agency with GC (awaiting verification)  
       
project team
       
owner Minshall Stewart Properties http://www.msscompany.com/
construction manager Appian Realty Advisors, LLC http://www.appianllc.com/
architect FOX Architects http://www.fox-architects.com/
civil engineer Vika http://www.vika.com/
structural engineer Rathgeber/Goss Associates http://www.rath-goss.com/
mep engineer META Engineers http://www.meta-eng.com
vertical transportation Lerch Bates & Associates, INC http://www.lerchbates.com/
fire, code & life safety Schirmer Engineering http://www.schirmereng.com/
zoning attorney Pillsbury Winthrop Shaw Pittman LLP http://www.pillsburylaw.com/
general contractor James G. Davis Construction Corporation http://www.davisconstruction.com/
     
project constraints
 
applicable codes International Building Code 2000
  International Mechanical Code 2000
  International Plumbing Code 2000
  National Electric Code 1996
  International Energy Conservation Code 2000
  ADAAG Latest Edition
  (Americans with Disabilities Act Accessibility Guidelines)
  Underwriters Laboratories, Inc. 1998
  District of Columbia Construction Codes 2003
  DCMR 13 Electrical and Mechanical  
  DCMR 13A Elevators  
  DC Law 8-36 Environmental Policy Act 1989  
  DCMR 12A Building Code Regulations 2003
  DCMR 12J Existing Building Code 2000
     
zoning DCMR Title 11 dated February 2003 http://dcoz.dc.gov/info/reg.shtm
  District of Columbia Zoning Map Map 10
  C-3-C Commercial District  
  F.A.R. by Right 6.5
  Allowable Floor Area 95,504.5 gross square feet
  Max Percentage of Lot Occupancy 100%
  Max Building Height by Right 90 feet
  with T.D.R.'s 130
  (Transfer Development Rights)  
  Number of Floors above Grade No Limit
  Required Parking  
  General Office 1 every 1,800 g.s.f. above 2,000 g.s.f.
  Retail Use 1 every 750 g.s.f. above 3,000 g.s.f.
  Penthouse Max Height 18'-6" with 1:1 set back
     
historical requirements none  
     
architecture
     
design and function The scope of this project includes the addition of three stories onto an existing occupied eight story building, extending the existing bank of three elevators while modernizing them up to a new elevator machine room on the penthouse level, and constructing a new penthouse and installing the necessary equipment.  Taking a step back this project sits on Washington Circle which is located in a commercial district in the North West part of Washington DC at the intersection of 22nd and K Street.  This project, as mentioned above, includes adding a Image Courtesy of DAVIS Construction
  three story steel structure with a penthouse onto an eight story concrete building constructed in the 1970’s.  The façade of the new construction was designed to complement the existing portion of the building.  There are several new additions to the exterior of the building.  One of which is Tnemec Enviro-crete paint.  The building from ground level to the eighth floor is getting a new coat of white paint to help it blend in with the new curtain wall system used on the ninth thru eleventh floors.  As previously mentioned, the façade of the three new floors is comprised of a curtain wall system, ribbon windows, punch windows, metal panes, and a screen system.  To make the buildings look more continuous throughout the entire height, an intricate louver system will be integrated into both new and existing construction.  One additional feature of interest to the building is the installation of a green roof on a portion of the ninth floor.
   
building enclosure
     
building facade The existing building is brick which will be receiving a coating of Tnemec Enviro-crete paint. On the South and West elevations, a unitized curtain wall systems will be used. This system will be exterior glazed. Each unit is one floor in height and four feet wide. The North elevation is comprised of masonry with Henry Airbloc over sheating with punched windows. The masonry is covered with the same Tnemec paint as mentioned above but this is not intended to be the primary measure against water infiltration. Image Courtesy of DAVIS Construction
  The façade will drain at each floor slab where there will be an EPDM flashing system. These punched windows are also exterior glazed. Along with the punch windows, the North elevation will feature composite metal panels over the same Henry Airbloc sheathing. As for the East elevation, ribbon windows with masonry over Henry Airbloc over sheathing at spandrel areas will be used. The masonry assembly is of the same nature as on the North in terms of water resistance. Finally, the penthouse will be covered in ribbed composite panels with a Tyvek vapor barrier over sheathing.
   
roofing The penthouse roof is comprised of several materials, first of which is the metal decking it all rests on. The roof deck used on this project is 3" deep rib, 20 gage galvanized metal deck. Above the metal deck sits a layer of rigid insulation which is to taper toward the roof drains to promote proper drainage. Next, there is a layer of single ply EPDM roof membrane with a gravel ballast. At all perimeter conditions, the EPDM must be continuous up and over the parapet and extend down as to overlap the facade material by two inches. Where there is to be a walkway there is to be Image Courtesy of DAVIS Construction
  two layers of a protective mat above the roof membrane and place roof pavers above.
   
  The other type of roofing is located on a portion of the ninth floor. In this location, a green roof was utilized. This roofing systems begins with the building existing roof as the substrate. Above this is the roofing membrane which is comprised of two layers of hot fluid applied roofing material. Next, there is a layer of felt followed by a protective layer, rigid insulation, moisture retention mats where needed, and filter fabric. On top of it all is a layer soil and vegetation which is to be at least three inches thick but not more than six inches thick and shall weight no more than eighteen pounds per square foot for a three inch green roof.

Awaiting Image of Green Roof

   

 

interior rendering
 
Link to FOX Architects' Website